What happened
On 19 July 1989, United Airlines Flight 232, a McDonnell Douglas DC-10-10, suffered a failure of its No. 2 tail engine, a GE CF6-6D, at 1516:10. There were 296 people aboard: 285 passengers and 11 crew. The NTSB report counts 111 fatalities, including one passenger who died 31 days later. The stage 1 fan disk was made at GE Evendale, Ohio, in 1971 and is described as a machined titanium alloy forging. At the accident, the disk had accumulated 41,009 hours and 15,503 cycles.
What the investigators found
The NTSB report states that a fatigue crack began at a small cavity on the bore surface, about 0.86 inch aft of the bore's forward face. The origin was a nitrogen-stabilised hard alpha inclusion around the cavity. The fatigue zone measured 1.24 inches axial by 0.56 inch radial depth. Striation counts correlated reasonably well with takeoff and landing cycles, indicating crack growth since early in the disk's life. A sister disk, S/N MPO 00388, had a similar inclusion with microcracks but no fatigue propagation.
The disk passed six fluorescent penetrant inspections: September 1972, November 1973, January 1976, June 1978, February 1982 and February 1988. Five were at United's San Francisco overhaul shop; one was at GE Ontario, California, in 1973. The last inspection was 760 cycles before the accident.
The NTSB probable cause was inadequate consideration given to human factors limitations in the inspection and quality control procedures at United's overhaul facility, leading to failure to detect a fatigue crack from a previously undetected metallurgical defect made by the manufacturer. The disk disintegration released debris that exceeded the protection of the hydraulic systems.
Why it matters for materials and inspection
The report links the crack origin to a material feature: a nitrogen-stabilised hard alpha inclusion around a bore-surface cavity. It also records that the disk passed six fluorescent penetrant inspections and that the last was 760 cycles before the accident, while the fatigue evidence indicates growth from early in the disk's life. In our view, these points make the case relevant to both material cleanliness and the reliability of repeated inspection; they do not support treating a passed inspection as proof that no crack exists.
What changed
Report section 1.17 records titanium melting and inspection history. After a 1970 separation in Rome, Italy, linked to a Type II segregate in argon-remelted material, the FAA and US Air Force required double-vacuum-melted material as the minimum for future critical rotating parts. In 1971 GE required triple-vacuum melting and the CF6-6 stage 1 fan disk drawing was changed to match. The current GE specification adds a hearth melting plus vacuum-arc remelting class intended to improve dissolution of hard alpha inclusions. Billet diameter was reduced to 10 inches, allowing more sensitive immersion-ultrasonic inspection. The current immersion-ultrasonic inspection uses 6 dB gain instead of 12 dB in 1971; the report estimates this lowers sensitivity by about 50 percent for most scan modes, though other changes affect the comparison. The macroetch procedure now has a second step using an ammonium bifluoride solution; fluorescent penetrant inspection continues with improved products and techniques.
Takeaways for engineers
The report records a hard alpha inclusion, a fatigue crack that grew from early in the disk's life, and six fluorescent penetrant inspections before failure. It also records changes to the melting route, billet diameter, immersion-ultrasonic inspection and macroetch.
In our view, engineers should treat inspection as a process with material, procedural and human variables, and should ask how detection margins are demonstrated when methods or specifications change.
Source. NTSB Aircraft Accident Report NTSB/AAR-90/06, United Airlines Flight 232, McDonnell Douglas DC-10-10, Sioux Gateway Airport, Sioux City, Iowa, 19 July 1989. NTSB report (FAA copy). This article summarises the sources in our own words; see the originals for full details. It is general technical information, not advice on a specific component.
Related reading
- Follow MTIS on LinkedIn for new failure reviews and industry briefings.
A crack your inspection should have found?
Send us the part history and inspection records for a failure investigation. Request a project quote